Ameriqual MRE Facility

This project was an extremely fast tract project. The design and presentation took 13 days with construction starting 5 days later.  The facility was producing product 7 months from the day the project hit my desk. The fast tracking of the project was due to the need for the product in the Gulf War.
The lake in the photos are for cooling, a part of the processing operations.